DEVELOPMENT SCHEDULE DETAIL

  week 1 week 2 weeks 3 weeks 4 weeks 5 weeks 6 weeks 7 weeks 8 weeks 9 weeks 10 weeks 11 weeks 12
Phase I Pre-Construction:
1. Project Planning (completed)
2. Determine project scope, goals, and objectives. (completed)
3. Obtain necessary permits and approvals. (in progress)
4. Create a budget. (completed)

Phase II Design
1. Develop architectural plans and engineering drawings. (completed)
2. Obtain structural engineering approval. (completed)
3. Finalize design and material selection. (completed)
4. Create a detailed project schedule. (completed)

Phase III Construction:
1. Site Preparation (completed)
2. Clear construction site. (completed)
3. Provide temporary utilities (completed)
4. Establish safety measures. (completed)
5. Foundation Construction (completed)
6. Excavate and place footings. (completed)
7. Pour concrete footings. (completed)
8. Allow time to dry. (completed)
9. Frame Construction
10. Build the Frame.
11. Install roof trusses or joists.
12. Finish exterior walls.
13. Floor Installation
14. Install roofing.
15. Insure proper insulation and ventilation.
16. Exterior Finishing
17. Install siding, Plaster & Cement
18Install windows and doors.
19. Finish roof details.
20. Initial Interior Installation
21. Install plumbing, electrical, and HVAC systems.
22. Finish walls and ceilings
23. Interior Finishing
24. Install drywall and paint.
25. Install flooring.
26. Cabinets and countertops.
27. Interior trimming and fittings.
28. Final Inspection and Testing
29. Inspect all systems and finishes.

IV POST-CONSTRUCTION
1. Post-Construction Phase:
2. Punch List and Finishing Touches
3. Address any remaining issues or deficiencies.
4. Final cleanup and preparation for occupancy.
5. Occupancy and Handover
6. Obtain occupant’s permission.
7. Hand over keys to owner.